The arch over the Ocean Avenue end of the Santa Monica Pier has stood there for 85 years. This week it was scheduled to come down. Crews were to start on Monday, Oct. 19, disconnecting the power and taking out the neon tubing to be crated. Then a crane would lift the sign itself off on Tuesday, Oct. 20. The City said ahead of time that construction dates can shift, so the exact day may have moved.
The entrance under the sign moved four months earlier, in June. For the rest of the $35.6 million Pier Bridge Replacement Project, which runs through late 2027, the Pier works on temporary routes, timed closures and a replica sign. It also has a monthly calendar written for the people who live close enough to work around all of that.
A Crane, a Crate and a Restoration Shop
According to the City Manager's update that Santa Monica Next republished on Oct. 13, the sign is going to Las Vegas, where the sign company YESCO will restore it. The update was direct about it:
"The most important thing to know is that the sign is not going away for good, and it is not being replaced!"
The plan is to reinstall it in mid- to late 2027, a little north of where it stood and a bit higher, for better clearance and visibility. So the sign that comes back will sit in a slightly different spot over a different bridge. The City has posted a Pier sign fact sheet for anyone who wants the details.
You can still get a picture with the sign in the meantime. According to the City's Oct. 13 update, a half-scale replica has stood on the Pier deck next to Pier Burger since last fall, and it's lit at night. For the next year or so, the replica is the Pier's sign.
The Entrance Moved in June
The sign is coming down because of the bridge under it. The bridge from Ocean Avenue dates to 1939 and no longer meets modern seismic standards. Construction began in December 2025. On June 5, 2026, a temporary pedestrian bridge opened about 30 feet south of the old entry. The City has said it will remain the Pier's primary entrance for the rest of the project, and the old Ocean Avenue entrance closed once it opened.
The City's June announcement lists four ways onto the Pier on foot:
- The temporary pedestrian bridge from Ocean Avenue, which has artwork, wayfinding signs and spotlights on Pier businesses along the way.
- Ocean Front Walk.
- The protected walkway along the temporary vehicle ramp in the Pier parking lot.
- The stairs near Bubba Gump Shrimp Co.
Cyclists have one important difference. Bikes, skateboards and other small vehicles are not allowed on the temporary pedestrian bridge, and the City sends them to Seaside Terrace instead. If you ride down Ocean Avenue to the Pier, your old line straight onto the deck is closed until the new bridge opens.
Driving In Through Late November
The fall phase added car detours. The City's Sept. 24 notice closed the Moomat Ahiko Way on- and off-ramps at Pacific Coast Highway for about two months, starting as early as Monday, Sept. 28. The closure lets crews demolish the last section of the old bridge and build its new columns. Counting two months from that start date puts the reopening around late November, if the schedule holds.
The posted detours work like this:
- Southbound on PCH: take the California Incline, or continue to eastbound I-10 and Lincoln Boulevard.
- Ocean Avenue to northbound PCH: use the California Incline.
The Pier stayed open throughout, with cars reaching it by other routes and parking. The Santa Monica Pier Corporation's directions page tells rideshare riders to use 1550 Appian Way and reach the deck by stairs or accessible ramps.
Morning walkers and runners have their own detail to plan around. The City's construction page says Ocean Front Walk under the bridge can close intermittently on weekdays between 5 a.m. and 1 p.m. Flaggers walk pedestrians around the short closures, and the page gives no end date. A weekend morning or a weekday afternoon keeps you clear of that window.
What Happens Under the Bridge Next
Taking the sign down is one step in a sequence, and most of the remaining work happens underground. The City's September construction update describes the ramp closure as the window to demolish the last of the old bridge. Foundation drilling, shoring, falsework and new bridge columns follow. The City's construction page says crews are now building the foundation by drilling and concreting deep columns, working from the Pier end toward Ocean Avenue.
Here are the dates the City has published:
- Dec. 2025: construction begins.
- June 5, 2026: the temporary pedestrian bridge opens and the old entrance closes.
- As early as Sept. 28, 2026: the Moomat Ahiko Way ramps close for about two months.
- Oct. 19–20, 2026: the Pier sign is scheduled to be removed and sent to YESCO.
- Mid- to late 2027: the restored sign goes back up.
- Late 2027: the new bridge is complete, ahead of the 2028 Olympic and Paralympic Games.
The new bridge will be 447 feet long. It will have a 15-foot sidewalk on its south side and a 75-year service life. The temporary bridge also sits on the south side, so the walk in from Ocean Avenue will look much the same once the permanent bridge opens: a wide path on the south edge with the sign above it, back on its new mount a little to the north.
A Calendar Programmed for Locals
The Pier is busy with bridge work for another year, and its own calendar during that stretch is aimed at nearby residents. Locals' Night is a free series on the third Thursday of every month from September through May. The Pier calls it a series "for locals, by locals," with youth activities, a car show, local DJs and bands, and art exhibits. October's edition on Oct. 15 marked 50 years of Dogtown. It featured a drive-in screening, a vinyl DJ set by Z-Boy Tony Alva, and a skate ramp.
The Pier has announced themes for the next two nights. November is Swiss Art + Sound, and December is Holiday Cheer on the Pier. Under the third-Thursday rule, those fall on Nov. 19 and Dec. 17. Tickets are free, but it's still worth checking the Pier's listing that week.
The Pier's happenings calendar also lists:
- Día de los Muertos on Sunday, Nov. 1.
- A Walk Through Pier History every Saturday and Sunday at 10 a.m. and Mondays at 6 p.m.
- A Talk Through Pier History, a free storytelling session from 6 to 7 p.m. on the last Thursday of the month.
- Giving Tuesday on Dec. 1, and Holiday Cheer on the Pier through December.
The history walk is a good fit for this year, since it covers a structure whose most famous piece is set to spend the next year in a Las Vegas restoration shop.
The next new tenant may also be aimed at locals. On Oct. 13, the City Council took up a request to authorize the City Manager to negotiate a lease with Santa Monica Brew Works for 256 Santa Monica Pier, the space Rusty's Surf Ranch used to occupy. That's according to coverage in the Santa Monica Daily Press and the Santa Monica Lookout. The Lookout described the concept as a surf-, skate- and beach-themed fast-casual restaurant with beer and live music, tentatively called "Surf Shack." The vote was only on whether to start negotiating, so a signed lease and an opening date would come later.
For the next year, the Pier you visit will have a replica sign by Pier Burger, a temporary bridge 30 feet south of the old entrance, and a free Locals' Night every third Thursday. The full sign returns in 2027.
At Pence Hathorn Silver, we follow the projects reshaping Santa Monica's coastline, from the Pier bridge to the streets around it, because they shape how this city lives day to day. If you'd like a local's read on how the 2027 Pier and its new entrance could affect the blocks closest to the beach, we'd be glad to talk. Schedule a Free Consultation.